Quote:
Originally Posted by simon varley
very good question. there were non-disclosure agreements flying around all over the place. I used to manage the prototype fleet, and the first I even know someone had build prototypes, was when some rocked up at the PG and somebody asked us to register them.
and to answer the question best I can - the rest of FoA were deep in the launch of next gen ranger so I don't think there was any spare resource.
|
They didn’t want extra work ie the F150 project interfering with their Aus engineering staff layoffs
Simple
Just subcontract the 150 programme out and we can reduce our FTE number